Here are the road projects underway in Hall County, and 8 on the horizon
04292018 EXIT 04.jpg
Construction continues Thursday, April 26, 2018, at the exit 14 interchange along Interstate 985. - photo by David Barnes

As Hall County grows, so does its list of road projects — ones that are underway and those to come.

Officials with the Georgia Department of Transportation, Gainesville-Hall County Metropolitan Planning Organization and city of Gainesville described several projects during the Greater Hall Chamber of Commerce’s Annual Transportation Forum Thursday, March 7.

“It’s truly an economic development phrase: Traffic is a sign of success for a community,” Gainesville City Manager Bryan Lackey said to a crowd at University of North Georgia’s Gainesville campus.

Flashing a picture on the screen above him of traffic backed up on Jesse Jewell Parkway, he added, “Obviously, we’re very successful.”

03082019 ROADS 1.jpg
Visitors to the annual transportation forum Thursday, March 7, 2019, Continuing Education Auditorium to capacity at the University of North Georgia Gainesville campus. - photo by Scott Rogers

These are the projects underway in Hall:

  • widening of Atlanta Highway/Ga. 13 from Sawnee Avenue to Lanier Islands Parkway/Ga. 347 in Buford

  • widening Ga. 347 from Lanier Islands resort to McEver Road

  • construction of a new interchange, Exit 14, between Oakwood and Flowery Branch

  • new bridges on Cleveland Highway/U.S. 129 and Browns Bridge Road/Ga. 36

  • widening Athens Highway/U.S. 129 from Gillsville Highway to the Talmo bypass

01062019 CONNECTOR 001.JPG
Cars drive though the intersection at Dawsonville Highway and McEver Road on Thursday, Jan. 3, 2019. A continuous flow intersection and some other alternatives are being considered to deal with the traffic issue. - photo by Austin Steele

Here’s a look at projects that are on the horizon:
Ga. 53 Bridge replacement

The westbound bridge on Dawsonville Highway/Ga. 53 over the Chattahoochee River is slated for replacement, with the project possibly being awarded to a contractor in July 2019. Cost: $26 million

I-985 maintenance

A new resurfacing and restriping project is planned for the entire length of I-985, from Interstate 85 in Gwinnett to Exit 24 in Gainesville. The project, which would include new reflectors, would start later this month or in April. Cost: $1.7 million.

Major intersection improvement

Turn lanes will be added at Queen City Parkway/Ga. 60 and Ga. 369 in Gainesville, which did the preliminary engineering. The project could be awarded this summer. Cost: $3.6 million.

Howard Road fixes

A possible interchange at Ga. 365 and roundabout at the Lanier Technical College entrance. The project is in early phases, but the project could be built in 2022-23. Estimated cost: $14.5 million.

I-985 widening

The interstate is set to be expanded from four lanes to six lanes between I-85 and Mundy Mill Road in Oakwood. Construction could take place in 2022-23. Engineering is underway. Estimated cost: $87 million.

Spout Springs Road widening

Right of way acquisition is about to wrap up on one of Hall’s most eagerly awaited projects, with the project being awarded to a contractor later this year. The road would be widened in its first phase from Hog Mountain Road to Union Circle at a cost of $32 million. Phase two, from Union Circle to the Hall County line, hasn’t been funded.

New South Hall roundabout

A roundabout is planned at Martin Road and JM Turk Road, near the planned Exit 14 interchange off I-985. Work is expected to take place this summer while school is out of session. Cost: $640,000.

Sardis Road Connector

One of Hall’s oldest projects could be coming to fruition early next decade. The nearly $80 million project calls for a four-lane road between Dawsonville Highway/Ga. 53 in West Hall and Thompson Bridge Road/Ga. 60 in North Hall.