By allowing ads to appear on this site, you support the local businesses who, in turn, support great journalism.
Parking deck completion pushed back again
0906deck
Detail brick work continues as the new Georgia Mountains Center parking deck nears completion sometime this fall. - photo by Tom Reed

Though it looks nearly complete from the outside, a completion date for Gainesville’s downtown parking deck is still at least a month away, according to project manager Jarrett Nash.

City officials originally planned to have the deck completed by July, but a problem with concrete and the summer’s above-average rainfall totals pushed the project’s completion date to September, Nash said.

Now, Nash says the deck may not be completed until mid-October, at the earliest. He said the contractor building the deck, Optum Construction, will update the City Council on the parking deck’s progress at a meeting Thursday.

"They’re pursuing it hard to get it finished," Nash said.

Nash says city officials spent last week meeting with contractors and architects to nail down a completion date in the hopes of having the deck ready for downtown fall events.

Designed by architect Steve Hill of Gainesville, the new $6.85 million parking deck will extend over the entrance to the mountains center and will include brick accents fashioned in a pattern similar to that on the downtown square sidewalks.

The four-level deck will accommodate 419 vehicles when complete and is designed to allow growth to a six-level deck.

Until the work is complete, only one lane of traffic will be open on Main Street from Spring Street to Broad Street. Main Street is open to one-way traffic leaving the square from Spring Street to Broad Street.

For drivers going to the downtown square, city officials recommend using Spring Street via West Academy Street.