Delays add $151,000 to cost of Forsyth County water plant expansion project

POSTED: June 20, 2012 11:30 p.m.

The expansion of Forsyth County’s water treatment plant is about three months behind schedule.

Barry Lucas, deputy director of water and sewer, said the delay will result in an additional $151,000 being paid to hired project manager CH2MHill.

The contractor, Garney Construction, is more than 100 days past the scheduled completion date of April 2, Lucas said.

Officials have attributed the delays to unforeseen technical issues.

The change was discussed at a Monday meeting of the water and sewer committee, which includes County Commissioners Patrick Bell and Brian Tam.

Jun. 20, 2012 11:48p.m. EDT Delays add $151,000 to cost of Forsyth County water plant expansion project Gainesville Times

The expansion of Forsyth County’s water treatment plant is about three months behind schedule.

Barry Lucas, deputy director of water and sewer, said the delay will result in an additional $151,000 being paid to hired project manager CH2MHill.

The contractor, Garney Construction, is more than 100 days past the scheduled completion date of April 2, Lucas said.

Officials have attributed the delays to unforeseen technical issues.

The change was discussed at a Monday meeting of the water and sewer committee, which includes County Commissioners Patrick Bell and Brian Tam.

Copyright 2011 MorrisMultimedia . All rights reserved. This material may not be published, broadcast, rewritten or redistributed


Comments

Commenting not available.
Commenting is not available.

LOCAL

SPORTS

LIFE & GET OUT

LOCAL VIDEO


Contents of this site are © Copyright 2010 The Times, Gainesville, GA. All rights reserved. Privacy policy and Terms of service

Powered by
Morris Technology
Please wait ...